Planning permission has official time limits. Councils are supposed to decide householder applications within 8 weeks and major developments within 13 weeks. But if you've ever spoken to someone who's been through the process, you'll know those targets are often missed by a wide margin.
Here's a realistic breakdown of how long the process actually takes — and what you can do to avoid the most common delays.
What are the planning approval patterns in your area?
Check your postcode — free, instant.
Check Your Postcode →The Official Timescales
- Householder applications (extensions, lofts, garden rooms): 8 weeks
- Minor applications (small new builds, changes of use): 8 weeks
- Major applications (10+ dwellings, large commercial): 13 weeks
- Applications requiring EIA: 16 weeks
These are the targets set by government. If a council misses them, the applicant can appeal to the Planning Inspectorate on the grounds of "non-determination." In theory, this keeps councils honest. In practice, many councils routinely negotiate "extensions of time" with applicants — formally extending the deadline by agreement.
What Actually Happens
The 8-week clock starts when your application is validated — not when you submit it. Validation itself can take 1-2 weeks, sometimes longer. If documents are missing, the council sends it back and the clock doesn't start until you resubmit.
So the real timeline for a typical householder application looks more like this:
- Weeks 1-2: Validation — council checks your application is complete
- Weeks 2-5: Consultation — neighbours notified, 21-day response window
- Weeks 5-8: Assessment — planning officer reviews, may request amendments
- Weeks 8-10: Decision — if straightforward, delegated decision issued
- Weeks 10-14: If flagged for committee — wait for next committee date
For a straightforward rear extension with no neighbour objections and no policy issues, 8-10 weeks from submission is realistic. But add one complication — an objection, a request for amended plans, or a committee referral — and you're looking at 12-16 weeks easily.
Why Some Councils Are Slower Than Others
Council planning departments have been under severe pressure for years. Budget cuts, staff shortages, and increasing application volumes mean that many teams are operating well beyond capacity.
Some councils — particularly larger urban authorities — have backlogs of several weeks before a planning officer even looks at a new application. Others, typically smaller district councils with lower volumes, can process applications closer to the 8-week target.
London boroughs are often the slowest. Inner London councils deal with complex sites, conservation areas, and high volumes of objections. It's not unusual for a householder application in Camden or Islington to take 12+ weeks even without complications.
By contrast, many councils in northern England and Wales process applications faster, partly because volumes are lower and partly because sites tend to be less constrained.
See what gets approved in your council →The Biggest Causes of Delay
Invalid applications. The single most common cause of delay. If your application is missing a document — a location plan, a biodiversity checklist, a design and access statement — it won't be validated. You'll get an email asking for the missing item, and the clock resets. This alone can add 2-4 weeks.
Neighbour objections. An objection doesn't mean refusal, but it does mean the planning officer has to address the issues raised. If the objection raises material planning concerns, the officer may ask you to amend the scheme. Amendments require a further round of consultation — and the clock effectively restarts.
Requests for amended plans. If the officer thinks the scheme could be approved with changes, they'll negotiate. This is usually a good sign — they're trying to get you to a yes. But each round of amendments adds 2-4 weeks.
Committee referral. Most householder applications are decided by officers under delegated authority. But if a ward councillor "calls in" the application, or if there are more than a certain number of objections (the threshold varies by council), it goes to the planning committee. Committee meetings happen monthly. If you miss the agenda deadline for the next meeting, you wait another month.
Specialist consultees. Applications near rivers need Environment Agency input. Sites near heritage assets need Historic England. These bodies have their own response times, and they don't always meet them.
How to Minimise Delays
You can't control everything, but you can avoid the most common self-inflicted delays:
- Check your council's validation checklist before submitting. Every council publishes one. Follow it exactly. Missing a single document is the most avoidable delay in the system.
- Use pre-application advice. Most councils offer a paid pre-app service (typically £100-£300 for householder proposals). This flags potential problems before you spend money on a formal application.
- Talk to your neighbours first. An objection slows everything down. A conversation over the fence before you submit can prevent one.
- Respond to officer queries quickly. When the planning officer emails asking for clarification or amended plans, don't sit on it. Every day you delay is a day added to the timeline.
- Submit online. Paper applications take longer to validate. Online submissions through the Planning Portal are processed faster by most councils.
What Happens After Approval?
Once you get the decision notice, planning permission is valid for three years. You must "commence development" within that period — which in practice means digging the foundations or starting meaningful construction work.
Your approval will come with conditions. Some need to be discharged (formally approved by the council) before you start work — for example, materials samples or construction management plans. Discharging conditions is a separate application, currently costing £43 per request in England, and typically takes 6-8 weeks.
You'll also need Building Regulations approval, which is a separate process from planning. Don't confuse the two — planning permission and building regulations cover different things.
The Bottom Line
Expect 10-14 weeks for a typical householder application, from submission to decision. Simple schemes in fast councils can be quicker. Complex schemes in busy councils can take much longer.
The biggest variable isn't the council — it's the quality of your application. A complete, well-prepared submission with no validation issues and a design that fits local policy will almost always move faster than one that needs fixing along the way.
And the foundation for a good application is understanding what your council actually approves. That's where the data comes in.
Planning outcomes depend on what's already been approved near your property.
Enter your postcode for a free instant approval check — or unlock the PlanningLens Pro Report (£79) with nearby planning decisions, refusal patterns, and ward-level analysis.
Check Your Postcode →Related Reading
How much does planning permission cost?
Why councils refuse planning permission
Planning permission vs building regulations
Do garden rooms need planning permission?